Minton Treharne & Davies – Specialist Laboratory installation
Project description
Ice Solar PV & Electrical Services were approached directly by the client, to install all electrical and data requirements to their new facility in Cardiff. ICE removed all electrical infrastructure from the building and refitted as per clients requirements over a 1 year contract period. ICE fitted out all labs with small power and lighting, a new CAT6 data network was installed along with all Fibre Optic links and data cabinets.
New distribution boards were fitted, and 400 amp 3 phase bus bars were installed throughout the building. Contract period 12 months with a value of £400,000.